Subpart D: Post-award requirements 2024 Uniform Guidance · effective Oct 1, 2024

2 CFR 200.340: Termination

2 CFR 200.340 sets 3 requirements for organizations that receive federal grants and cooperative agreements. Applies while you manage a federal award.

Shows up in your application: Risk management planCertifications and assurancesOrganizational capacityCloseout plan

What 2 CFR 200.340 requires

1. General

What you must do

The award may be terminated in part or entirety: (1) by the agency/PTE for noncompliance with award terms; (2) by mutual consent with agreed conditions; (3) by the recipient/subrecipient on written notice of reasons, effective date, and portion (though the agency/PTE may terminate the whole award if the remainder will not accomplish its purposes); or (4) pursuant to award terms and conditions, including — to the extent authorized by law — if the award no longer effectuates program goals or agency priorities; all termination provisions must be clearly and unambiguously specified in the award terms.

When it applies

Any termination event during the period of performance

Risk management planCertifications and assurances
2. Disclosure

What you must do

When the agency terminates for the recipient's material failure to comply, it must report the termination in SAM.gov (entered via CPARS) — but only after the recipient exhausts its § 200.342 objection rights or lets 30 calendar days pass without signaling appeal; erroneous entries must be corrected within three business days, and FOIA-exempt information must not be publicly posted (with a 7-day removal procedure on the recipient's assertion).

When it applies

Federal agency terminates the award for the recipient's material failure to comply

Organizational capacityCertifications and assurances
3. Closeout

What you must do

After any partial or complete termination, the agency/PTE and the recipient/subrecipient remain responsible for closeout (§ 200.344) and post-closeout adjustments and continuing responsibilities (§ 200.345).

When it applies

Award terminated in part or in its entirety

Closeout plan
Grantable compliance database

Ask what 2 CFR 200.340 means for your award

Upload your award terms and ask what you owe and when. Grantable answers from its compliance database of federal, agency and state rules, with citations.

Sections 2 CFR 200.340 refers to

Sections that refer to 2 CFR 200.340

Regulation text of 2 CFR 200.340

+

(a) The Federal award may be terminated in part or its entirety as follows:

(1) By the Federal agency or pass-through entity if the recipient or subrecipient fails to comply with the terms and conditions of the Federal award;

(2) By the Federal agency or pass-through entity with the consent of the recipient or subrecipient, in which case the two parties must agree upon the termination conditions. These conditions include the effective date and, in the case of partial termination, the portion to be terminated;

(3) By the recipient or subrecipient upon sending the Federal agency or pass-through entity a written notification of the reasons for such termination, the effective date, and, in the case of partial termination, the portion to be terminated. However, if the Federal agency or pass-through entity determines that the remaining portion of the Federal award will not accomplish the purposes for which the Federal award was made, the Federal agency or pass-through entity may terminate the Federal award in its entirety; or

(4) By the Federal agency or pass-through entity pursuant to the terms and conditions of the Federal award, including, to the extent authorized by law, if an award no longer effectuates the program goals or agency priorities.

(b) The Federal agency or pass-through entity must clearly and unambiguously specify all termination provisions in the terms and conditions of the Federal award.

(c) When the Federal agency terminates the Federal award prior to the end of the period of performance due to the recipient's material failure to comply with the terms and conditions of the Federal award, the Federal agency must report the termination in SAM.gov. A Federal agency must use the Contractor Performance Assessment Reporting System (CPARS) to enter information in SAM.gov.

(1) The information required under paragraph (c) of this section is not to be reported in SAM.gov until the recipient has either:

(i) Exhausted its opportunities to object or challenge the decision (see § 200.342); or

(ii) Has not, within 30 calendar days after being notified of the termination, informed the Federal agency that it intends to appeal the decision to terminate.

(2) If a Federal agency, after entering information about a termination in SAM.gov, subsequently:

(i) Learns that any of that information is erroneous, the Federal agency must correct the information in the system within three business days;

(ii) Obtains an update to that information that could be helpful to other Federal agencies, the Federal agency is strongly encouraged to amend the information in the system to incorporate the update in a timely way.

(3) The Federal agency must not post any information that will be made publicly available in the non-public segment of SAM.gov that is covered by a disclosure exemption under the Freedom of Information Act (FOIA). When the recipient asserts within seven calendar days to the Federal agency which posted the information that a disclosure exemption under FOIA covers some of the information made publicly available, the Federal agency that posted the information must remove the posting within seven calendar days of receiving the assertion. Before reposting the releasable information, the Federal agency must resolve the issue in accordance with the agency's FOIA procedures.

(d) When the Federal award is terminated in part or its entirety, the Federal agency or pass-through entity and recipient or subrecipient remain responsible for compliance with the requirements in §§ 200.344 and 200.345.

Source: eCFR · checked Sep 17, 2026

Questions about 2 CFR 200.340

What does 2 CFR 200.340 require?

The award may be terminated in part or entirety: (1) by the agency/PTE for noncompliance with award terms; (2) by mutual consent with agreed conditions; (3) by the recipient/subrecipient on written notice of reasons, effective date, and portion (though the agency/PTE may terminate the whole award if the remainder will not accomplish its purposes); or (4) pursuant to award terms and conditions, including — to the extent authorized by law — if the award no longer effectuates program goals or agency priorities; all termination provisions must be clearly and unambiguously specified in the award terms. When the agency terminates for the recipient's material failure to comply, it must report the termination in SAM.gov (entered via CPARS) — but only after the recipient exhausts its § 200.342 objection rights or lets 30 calendar days pass without signaling appeal; erroneous entries must be corrected within three business days, and FOIA-exempt information must not be publicly posted (with a 7-day removal procedure on the recipient's assertion). After any partial or complete termination, the agency/PTE and the recipient/subrecipient remain responsible for closeout (§ 200.344) and post-closeout adjustments and continuing responsibilities (§ 200.345).

When does 2 CFR 200.340 apply?

Any termination event during the period of performance. Federal agency terminates the award for the recipient's material failure to comply. Award terminated in part or in its entirety.

Plain-English summaries for information only, not legal advice. Always check the regulation text, your award terms and your agency’s guidance.